Budgeted cost of work performed (BCWP), or "earned value" (EV), in project management
Project management
Project management is the discipline of planning, organizing, securing, and managing resources to achieve specific goals. A project is a temporary endeavor with a defined beginning and end , undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value...

 is the budgeted cost of work that has actually been performed in carrying out a scheduled task during a specific time period. NASA's definition of the BCWP is the sum of the budgets for completed work packages and completed portions of open work packages, plus the applicable portion of the budgets for level of effort and apportioned effort. BCWP is an Earned value management
Earned value management
Earned value management is a project management technique for measuring project performance and progress in an objective manner. EVM has the ability to combine measurements of scope, schedule, and cost in a single integrated system. Earned Value Management is notable for its ability to provide...

 term and it is different from:
  • Budgeted cost of work scheduled (BCWS) : the approved budget that has been allocated to complete a scheduled task during a specific time period.
  • Actual Cost of Work Performed (ACWP) : the actual cost that has been spent, rather than the budgeted cost.


As example of the difference assume that a schedule contains:
  • a task "Test hardware" that is budgeted to cost $1000 to perform, and
  • is expected to begin at the start of January 1 and
  • complete at the end of January 10.

At the end of January 5, the work is scheduled to be 50% complete (5 days of the scheduled 10 days). So, at the end of January 5,
  • the BCWS is $1000 (the budgeted cost) times 50% (the scheduled completion percentage), or $500.


Suppose that by the end of January 5, the work is actually only 30% complete. In this case,
  • the BCWP would be $1000 (budgeted cost) times 30% (the actual completion percentage), or $300.


Also, suppose that to reach the 30% complete level at the end of January 5, $250 was actually spent.
  • Then, the ACWP would be $250.