Severn Tunnel
The Severn Tunnel is a
railway tunnel in the
United Kingdom, linking
South Gloucestershire in the west of
England to
Monmouthshire in south
Wales under the
estuary of the
River Severn. It was built by the
Great Western Railway between 1873 and 1886, and is 4 mi 624 yd long, and is still the longest mainline railway tunnel within the UK . In 2007, the opening of Phase 2 of the
Channel Tunnel Rail Link will take this record away. Only 2 miles of the tunnel are actually under the river.
Prior to the building of the tunnel, communications between the
Bristol area and South Wales were primarily by boat.
Encyclopedia
The
Severn Tunnel is a
railway tunnel in the
United Kingdom, linking
South Gloucestershire in the west of
England to
Monmouthshire in south
Wales under the
estuary of the
River Severn. It was built by the
Great Western Railway between 1873 and 1886, and is 4 mi 624 yd long, and is still the longest mainline railway tunnel within the UK . In 2007, the opening of Phase 2 of the
Channel Tunnel Rail Link will take this record away. Only 2¼ miles of the tunnel are actually under the river.
Prior to the building of the tunnel, communications between the
Bristol area and South Wales were primarily by boat. With the coming of the railway, services were forced to either take a long detour via
Gloucester, or to transfer their passengers and cargo onto a
ferry. The GWR proposed to drive a tunnel under "The Shoots", a relatively narrow but unusually deep section of the estuary. This meant steep gradients by railway standards in order to reach the required depth.
Work on the tunnel began in March 1873, and proceeded gradually through the 1870s. As Thomas Walker notes in his book, GWR had expected the critical part of the work to be the tunnelling under the deep-water channel of the Shoots. However, the builders' real difficulties began in October 1879. At this stage, when only 130 yards remained separating the main tunnel heading being driven from the Welsh side, and the shorter Gloucestershire heading, the workings were inundated, from a large fresh-water source tapped by the heading being driven inland on the Welsh side.

Thomas A. Walker was the contractor entrusted by the chief GWR engineer Sir John Hawkshaw with rescuing and completing the tunnel after the 1879 flooding. Holding the Great Spring in check required the installation of greatly increased pumping facilities, and a diver had to be sent down a shaft and 300 m along the tunnel heading to close a door in the workings and seal off the waters. This troublesome task was finally achieved in November 1880 by lead diver Alexander Lambert using Henry Fluess' new
self contained breathing apparatus, but work in the area of the Great Spring was unable to continue until January 1881 when the Great Spring was temporarily sealed off. Work was later disrupted in 1883 by further flooding from the Great Spring, and again Lambert managed to save the day. Additional mishaps afflicting the workings included a large tidal wave and a breakthrough of the bed of a pool on the English side. In the intervening period the Severn Railway Bridge from Sharpness to Lydney was opened.
The tunnel was completed during 1885 and a goods train passed through it on January 9, 1886, but regular services had to wait until the pumping systems were complete. The tunnel opened to goods trains in September and to passenger traffic in December 1886, nearly 14 years after work had started. Fixed
steam engines pumped out the Great Spring and other sources of water until the
1960s, when they were replaced by electrically powered pumps.
The Second Road Crossing , which passes above the tunnel, crosses over it on a "ground level bridge" on the English side, , supported in such a way that no load is imposed on the tunnel. The opportunity was taken to renew the concrete cap above the tunnel in the Salmon Pool during bridge-construction.
There is also a second tunnel under the river just upstream near this point, carrying a high-capacity electricity cable under the river, and complementing the earlier high-capacity link, which is slung high over the river . Both electricity links were originally commissioned by the
CEGB.
During
World War II, a
Great Western Railway passenger train was pursued by a German aircraft along the main line to Wales. Reaching speeds estimated at 90mph the train successfully escaped into the tunnel and stopped beneath the river until the driver judged that the danger had passed. The train was struck by several bullets during the chase but there were no serious injuries.
References
- The Severn Tunnel: Its Construction and Difficulties by Thomas A. Walker ISBN 1-85026-014-1 reprinted edition 2004, Nonsuch Publishing Ltd, Stroud, England ISBN 1-84588-000-5 . .
- Railway Tales Of The Unexpected by K Westcott-Jones ISBN 0-946537-73-9, 1992, Atlantic Transport Publishers.
External links
- from the Great Western Archive
- , how divers tried to seal the Great Spring