HEC-RAS
Posts  1 - 1  of  1
Iffezheim
Hello!
I got questions about HEC-RAS.

1700 Xs
A Hydrograph of 10 years, Flow Duration 1 day
A barrage at the upstream end
3 tributaries (only water inflow, no sediment because of barrages within)

Appr.300 drediging sites
Appr.100 sites where sediment is added

Question #1:
Is it possible to change the channel uniformly within the moveable bed limits?
Lets say, all points minus 2 inches?

Question #2:
Similar to #1.
Lets say, all points plus 2 inches?
I have to raise the invert because sediment is added to the river in order to stop/minimize erosion.

Adding or removing material from the invert shall take place once a month within the 10-years-hydrograph.

Question #3:
Is it possible to stop the sediment modelling after time-step "N", change something at the channel (raise/lower the culvert), pass the results to time-step "N+1", an restart the sediment modelling again?

Thxs in advance.

Andreas